A 656-foot crane ship with two 7,826-ton cranes set 100 wind turbine foundations and two substation jackets into the Baltic in four months, lifting each steel tube off a transport vessel, swinging it

Americans got a pretty good look at the Thialf last year, when the giant crane ship dropped anchor in Narragansett Bay ahead of foundation work at Equinor's